My Wedding Candle Needs Six Hours Before Demoulding — How Many Identical Moulds Do I Need to Complete 500 Pieces Before the Event?
शेयर करना
What does that cost at CSI prices? At ₹942.82 a mould (Pillar Candle Mould, Daisy Pillar Mould and the Polycarbonate Pillar Candle Mould are all that price), ₹29,227.42 for 10 days, ₹40,541.26 for 7, ₹57,512.02 for 5. Squeezing 10 days into 5 costs ₹28,284.60 more in moulds.
Can I get more cycles from each mould? Yes: pour once more at 22:00 and let it set overnight. That is 3 cycles a day over a 15-hour span, and the 10-day count drops to 21 moulds (₹19,799.22).
What must I do first? Buy three moulds and time your real demould in the room you will produce in. At a 7-hour set, Plan A falls to one cycle a day and the 10-day count jumps from 31 to 61. Then confirm with us on WhatsApp that we can supply that many moulds of the same variant before you promise the client a date.
- Straight answer: count cycles, then moulds
- Your order as numbers
- How many cycles one mould gives you a day
- The mould count for 5, 7 and 10 production days
- The set-time cliff: why you time it before you buy
- Where the production days come from
- Identical means identical: buying 31 of one mould
- The moulds and materials in this plan
- Frequently asked questions
Your order as numbers
The title fixes two figures: 500 pieces and 6 hours before demoulding. Both are treated as yours and used exactly. The rest is a labelled worked example: pieces are demoulded, cleaned and the mould re-sealed and re-poured, with 30 minutes of hands-on time on each side of the set; you work a 14-hour day from 08:00 to 22:00; you hold back 10 extra pieces (two client samples, four retains, four for burn tests); and 6% of moulded pieces fail inspection (air pockets, a surface mark, an off-centre wick, a chipped edge). If your history says 3% or 10%, use that. The weight of one piece does not change the mould count at all, which is why this post does not need it; it matters for wax and melter capacity, covered briefly below and in full in 6356.
| Input | Figure | Source |
|---|---|---|
| Pieces delivered | 500 | your figure (title) |
| Hours before demoulding | 6 h | your figure (title); to be timed in your room |
| Planned extras | 10 pieces | worked example: samples, retains, burn tests |
| Loss buffer | 6% | worked example: moulded-piece rejects |
| Pours needed | 543 | (500 + 10) ÷ 0.94, rounded up |
| Hands-on per cycle | 0.5 h + 0.5 h | worked example: seal, wick, pour; demould, clean |
| Staffed day | 14 h (Plan A) or 15 h span (Plan B) | worked example |
| Production days | 10 in the worked calendar; 5 and 7 also shown | worked example |
Notice what is not on this list: a demould time from us. None of the CSI mould pages or the Soy Pillar Wax page states one in the text we captured. The Polycarbonate Pillar Candle Mould page only says "Allow it to cool completely before unmolding". Six hours is your measurement, and the plan is only as good as that measurement.
How many cycles one mould gives you a day
A mould is occupied from the moment you seal and wick it until it is clean and ready again: hands-on before, set, hands-on after. In the worked plan that is 0.5 + 6 + 0.5 = 7 hours. Divide the staffed window by the cycle and round down, because a cycle that cannot finish inside the day does not count.
Plan A: two cycles inside a 14-hour day
Pour at 08:00, set until 14:30, demould and re-pour by 15:30, set until 21:30, demould by 22:00. That is 14 ÷ 7 = 2 cycles, exactly. "Exactly" is the warning: there is no room in that day for the set to run long.
Plan B: a third cycle that sets while you sleep
The 6-hour set does not need you in the room. If someone pours one more round at 22:00 and someone demoulds at 07:30, each mould does 3 cycles a day: two in daylight and one overnight. The staffed span becomes 15 hours (or two overlapping shifts), but the hands-on hours barely change: you add one pour and one demould per mould. Leave the overnight pieces somewhere draught-free, where the room temperature does not swing (no AC switched off at midnight or open window at dawn), because the set time you measured was measured in a steady room.
The mould count for 5, 7 and 10 production days
Moulds = ceil(543 ÷ (cycles a day × production days)), then 10% spares rounded up. Spares cover a mould that tears, one that releases badly, and one that fails inspection on arrival; CSI pages state no cycle life for these moulds, so the spare figure is judgement, not data.
| Production days | Plan A (2 a day): working + spare = buy | Plan A cost | Plan B (3 a day): working + spare = buy | Plan B cost |
|---|---|---|---|---|
| 5 | 55 + 6 = 61 | ₹57,512.02 | 37 + 4 = 41 | ₹38,655.62 |
| 7 | 39 + 4 = 43 | ₹40,541.26 | 26 + 3 = 29 | ₹27,341.78 |
| 10 | 28 + 3 = 31 | ₹29,227.42 | 19 + 2 = 21 | ₹19,799.22 |
Read across the rows and the economics are plain. The 10-day Plan A costs ₹29,227.42 in moulds, ₹58.45 a piece across 500 pieces. The 5-day Plan A costs ₹57,512.02, ₹115.02 a piece. Adding the overnight cycle is the cheapest lever: on 10 days Plan B needs 21 moulds (₹19,799.22, ₹39.60 a piece). On 7 days Plan B (29 moulds) is cheaper than Plan A on 10.
| Line | Count | How it is worked out | Cost |
|---|---|---|---|
| Pieces the client receives | 500 | your figure (title) | |
| + planned extras | 10 | 2 client samples, 4 retains, 4 burn-test pieces (worked) | |
| + loss buffer | 543 pours | 510 ÷ (1 − 6%), rounded up | |
| Working moulds | 28 | ceil(543 ÷ (2 cycles × 10 days)) | ₹26,398.96 |
| + spares | 3 | 10% of 28, rounded up (tears, a bad release, a failed inspection) | ₹2,828.46 |
| Moulds to buy | 31 | bought as 3 for the trial (₹2,828.46) + 28 after it (₹26,398.96) | ₹29,227.42 |
| Leftover after the event | 31 moulds | 17 unused pour slots of 560; moulds reusable if the shape is |
Buying in two steps matters. Three moulds for the trial (₹2,828.46) tell you the real set time, the real reject rate and whether the shape releases cleanly; the other 28 (₹26,398.96) follow only when those numbers hold. If the trial shows 7 hours, you have learnt it for ₹2,828.46, not for ₹29,227.42.
Does the rest of the line keep up?
Moulds are usually the bottleneck, but check the melt. With a worked piece of 250 g (weigh one from your own mould), 543 pours is 135.75 kg of finished mix, and the busiest day on the 10-day plan (28 moulds × 2 = 56 pours) is 14.00 kg: 2 melts in a 10 kg melter. The Electric Wax Melter page says it "can melt 10 kg of soy wax in approximately 30 minutes at 100°C"; treat that as the maker’s claim, and melt to your wax’s working temperature, checked with a thermometer, not to 100°C. Hands-on time is the other limit: 56 pours a day at, say, 4 minutes of combined pour and demould work each is under 4 hours of labour, well inside the day. The three-constraint version (melt, moulds, people) for a different order is the 300-candles-in-10-days post.
The set-time cliff: why you time it before you buy
Because cycles are rounded down, the count does not rise smoothly as the set gets longer. It jumps. At 6 hours, Plan A fits two cycles with not a minute to spare; at 7 hours, the second cycle cannot finish before 22:00 and the day collapses to one cycle. The mould count for 10 days goes from 31 to 61 (₹57,512.02). Plan B is far more forgiving: at 7 hours it still gets two cycles (one by day, one overnight), and needs 31 moulds.
| Hours before demoulding | Cycle (set + 1 h hands-on) | Plan A cycles a day | Plan B cycles a day | Plan A moulds for 10 days |
|---|---|---|---|---|
| 5 h | 6 h | 2 | 3 | 31 |
| 6 h | 7 h | 2 | 3 | 31 (your figure) |
| 7 h | 8 h | 1 | 2 | 61 (₹57,512.02) |
| 8 h | 9 h | 1 | 2 | 61 |
Set times move with the room. Pieces that release at 6 hours in a cool October workshop can need longer in a warm room, and a hot spell or a different production space changes the figure again. Soy pillar wax that is still warm in the core can also crack or mark when forced. So time it where you will produce: pour three trial pieces at your production pour temperature, test one at 5 hours, one at 6, one at 7, and note the room temperature. If the 6-hour piece releases cleanly and the 5-hour one does not, your 6 hours is real and Plan A works; if only the 7-hour piece is clean, plan on Plan B or more days.
Where the production days come from
Start from the event and subtract everything that is not pouring. In the worked plan the event is 24 days away. Moulds take 4 days to arrive (a worked figure; we do not publish dispatch or transit times, so confirm on WhatsApp), 1 day to inspect, number and trial them, then after the last demould 3 days of cure before final QC (the Soy Pillar Wax page states no cure time in the text we captured, so this is your own approved figure; for soy, many makers wait longer before judging scent), 2 days for QC and packing, 1 for delivery, and 3 of slack. That leaves 10 production days, which is why the settling number in this post is the 10-day count.
| Block | Days | Why it cannot be squeezed |
|---|---|---|
| Moulds arrive (confirm with CSI) | 4 | Not published; ask before planning |
| Inspect, number, demould trial | 1 | Confirms the 6 h and the reject rate |
| Production | 10 | 55 pours a day on average |
| Cure after the last demould | 3 | Calendar time; QC on cured pieces |
| QC, wrapping, packing | 2 | Every piece checked against the retained sample |
| Delivery | 1 | Your courier or your own van |
| Slack | 3 | A day lost to a power cut or a bad batch |
| Event | day 24 |
The burn test is not in those days, and it must already be done
The worked calendar assumes the client has signed a sample piece made from this mould, wax, wick and oil, and that the piece has passed a burn test. A freestanding pillar burns differently from a container candle, and the wick choice for a moulded shape belongs to 6356. If that test has not happened, it comes first and it takes calendar time: pour, cure, burn over several sessions. Put a 7-day test round into the worked calendar and production falls to 3 days; Plan A would then need 101 moulds (₹95,224.82). That is the decision rule doing its job: at that point the honest answer is a new date, fewer pieces, or a simpler design, not a hundred moulds and an untested candle. Shortening cure for a deadline is its own question, answered in the cure-time-under-deadline post; standardising cure across pour days is 3158.
| Check | Why | Calendar time |
|---|---|---|
| Signed sample piece from the production mould, wax, wick and oil | The client approves what they will receive | Before mould purchase |
| Burn test of the moulded piece through several sessions | A freestanding shape can drip, tunnel or lean | About a week incl. cure (worked) |
| Demould trial at 5, 6 and 7 hours in the production room | Sets the cycle and the mould count | One day |
| Inspection of every mould on arrival | A flawed mould makes flawed pieces for 20 cycles | Part of the inspection day |
| Lot check when the wax or oil changes mid-order | A new lot can shift release or surface | A half-day trial pour |
Identical means identical: buying 31 of one mould
For a wedding table, every piece must match the approved sample. That means one listing and one variant: Pillar Candle Mould Tall and Short are different pieces, and so is the Polycarbonate Pillar Candle Mould at 16.3 cm by 4.1 cm. Within one variant, moulds made at different times can still differ slightly in finish or wall. CSI does not publish batch information for moulds, and we will not promise that 31 units come from one batch; ask on WhatsApp, and inspect what arrives.
The moulds and materials in this plan
Three moulds at the same price, the wax for the trial, and the sealer that keeps rigid moulds from leaking. Nothing is ranked on performance: CSI publishes no demould times or cycle lives for these moulds, so your trial decides. The Twisted Pillar Mould is out of stock on 7 October 2026 and is not offered.
| Variant | Price | Stock | Plan A, 10 days |
|---|---|---|---|
| Tall (11.2 cm x 6.3 cm) | ₹942.82 | In stock on 7 October 2026 (depth: ask) | 31 for ₹29,227.42 |
| Short (8.6 cm x 6.5 cm) | ₹942.82 | In stock on 7 October 2026 (depth: ask) | 31 for ₹29,227.42 |
| Variant | Price | Stock | Plan A, 10 days |
|---|---|---|---|
| Single mould | ₹942.82 | In stock on 7 October 2026 (depth: ask) | 31 for ₹29,227.42 |
| Variant | Price | Stock | Plan A, 10 days |
|---|---|---|---|
| Single mould | ₹942.82 | In stock on 7 October 2026 (depth: ask) | 31 for ₹29,227.42 |
| Size | Price | Per kg | Use here |
|---|---|---|---|
| 500 g | ₹300.00 | ₹600.00 | mould trial |
| 1 kg | ₹600.00 | ₹600.00 | mould trial top-up |
| 5 kg | ₹3,000.00 | ₹600.00 | |
| 10 kg | ₹6,000.00 | ₹600.00 | production (count from 6356) |
| Pack | Price | Stock | For 31 moulds |
|---|---|---|---|
| Pack (80 pieces per page) | ₹472.00 | In stock on 7 October 2026 | one pack, reused |
CandleMakingSuppliesIndia sells the moulds, wax and sealer in this plan and does not sell finished candles. This page still tells you to buy three moulds before thirty, to buy days rather than moulds when a rush would cost ₹28,284.60 more, and to confirm identical supply with us before you promise a client anything.
Every CSI price was checked on the live store on 7 October 2026; every mould and pack offered is in stock on that date, and the Twisted Pillar Mould, which is out, is not offered. CSI pages state no demould time, cycle life or batch information for these moulds, and stock depth, dispatch dates and batch continuity are not published: confirm them on WhatsApp.
The 500 pieces and the 6-hour set are your figures. The hands-on times, staffed hours, extras, 6% loss, 10% spares, piece weight, calendar and labour minutes are labelled worked examples; the arithmetic is shown so you can replace them. For bulk pricing, stock confirmation, GST invoicing, and MSDS and IFRA documentation on request, message us on WhatsApp at +91 7397976926.
Frequently asked questions
- I Need 500 Sculptural Wedding Candles — How Do I Calculate Mould Quantity as Well as Wax, Fragrance and Wick Requirements?
- A Wedding Client Wants 300 Candles in 10 Days — How Do I Calculate Whether My Current Moulds, Wax Capacity and Team Can Finish on Time?
- I Received a 500-Piece Wedding Candle Order in a Fragrance I Have Never Used Before — What Must I Test Before Buying 50+ Kg of Raw Materials?
- Should I Secure All Critical Custom Materials Before Promising a Final Wedding Delivery Date?
- A Wedding Order Requires Custom Fragrance, Custom Colour and Custom Packaging — How Much Extra Development Time Should I Build into Production?
- Which Raw Materials for a Custom Wedding Candle Should Be Client-Approved Before I Commit to Bulk Purchasing?
- How Do I Move a Wedding Candle Order from Sample Approval → Final Formula → Exact BOM → Bulk Raw-Material Purchase → Production → QC → Delivery?
- How Much Extra Inventory Should I Buy for Custom Wedding Materials That Cannot Easily Be Used After the Order?
Customer reviews: The six reviews at the top of this page are genuine, published Judge.me reviews left by CSI customers on the product pages named on each card — Eco Candle Wicks, Premium Candle Wicking Needle, Ribbed Pillar Mould (3 Different Sizes), Soy Pillar Wax (Specially made for Pillar and Designer Candles). They are general product reviews, not assessments of the bulk-order advice on this page. Names, star ratings, dates and products are as recorded by Judge.me and wording is unedited. "Verified buyer" appears only on reviews Judge.me recorded as verified — Deepika k., Delcy Fernandes, Jinal Patel, Monika Deep. The reviews from Lalitha Jagan, LJ are published but not recorded as verified, and carry no badge. Reviews below five stars are included as published, not filtered out.
Figures verified 7 October 2026, CSI live pricing: Pillar Candle Mould Tall (11.2 cm x 6.3 cm) ₹942.82, Short (8.6 cm x 6.5 cm) ₹942.82; Daisy Pillar Mould ₹942.82; Polycarbonate Pillar Candle Mould ₹942.82; Twisted Pillar Mould ₹824.82 (out of stock); Soy Pillar Wax 500 g ₹300.00, 1 kg ₹600.00, 5 kg ₹3,000.00, 10 kg ₹6,000.00; Candle Mold Sealer (for Pillar Candles) ₹472.00; Electric Wax Melter 10 kgs capacity ₹21,240.00, 20 kgs capacity ₹25,960.00. Stock depth, batch continuity and dispatch dates are not published: confirm on WhatsApp.
Non-price figures: 500 pieces and 6 hours before demoulding are the reader’s figures (title). The 30-minute handling steps, 14-hour day, 15-hour Plan B span, 10 extras, 6% loss buffer, 10% spare moulds, 250 g piece, 24-day calendar and its blocks, 4-minute handling labour and 7-day test round are labelled worked examples. Mould page wording is quoted as written, including the Pillar Candle Mould page’s two descriptions of its material. The melter page’s melt-time claim is attributed, not tested. This is practical judgement, not legal advice.