I'm Growing Quickly but Don't Want to Run Out of Wax — How Do I Set a Reorder Point Based on Monthly Consumption and Supplier Lead Time?

I'm Growing Quickly but Don't Want to Run Out of Wax — How Do I Set a Reorder Point Based on Monthly Consumption and Supplier Lead Time?

 

CSI 464 soy wax ₹507.40 / kg at every size Luxury Soy Wax Chunks ₹599.00 / kg Natural Soy Pearl ₹424.80 / kg from 5 kg
CSI candle business economics · Scaling, cash flow & procurement
A reorder point that grows with your sales, so the wax arrives before the shelf is empty.
★★★★☆
"Quality of the wick is good for jar candles, team can work on the pricing and delivery timelines."
Monika DeepVerified buyer · Oct 2025
Eco Candle Wicks
★★★★★
"Quality wick, works very well"
AshwiniSep 2025
Eco Candle Wicks
★★★★☆
"Good quality .... if possible delivery date would be try little bit quick please"
Subhankar RoyVerified buyer · Sep 2024
Eco Candle Wicks
★★★★★
"This needle is very helpful as it doesn't damage the mould and there is no leakage of wax while pouring.. I would definitely recommend this .."
LJAug 2024
Premium Candle Wicking Needle
★★★★★
"Good one"
Sneha TamangVerified buyer · Apr 2025
Premium Candle Wicking Needle
★★★★★
"This bamboo wick holder doesn't exert any pressure on the wicks… and it is a very useful product 👌🏻👌🏻.."
Lalitha JaganAug 2024
Bamboo Wick Holder
★★★★☆
"Quality of the wick is good for jar candles, team can work on the pricing and delivery timelines."
Monika DeepVerified buyer · Oct 2025
Eco Candle Wicks
★★★★★
"Quality wick, works very well"
AshwiniSep 2025
Eco Candle Wicks
★★★★☆
"Good quality .... if possible delivery date would be try little bit quick please"
Subhankar RoyVerified buyer · Sep 2024
Eco Candle Wicks
★★★★★
"This needle is very helpful as it doesn't damage the mould and there is no leakage of wax while pouring.. I would definitely recommend this .."
LJAug 2024
Premium Candle Wicking Needle
★★★★★
"Good one"
Sneha TamangVerified buyer · Apr 2025
Premium Candle Wicking Needle
★★★★★
"This bamboo wick holder doesn't exert any pressure on the wicks… and it is a very useful product 👌🏻👌🏻.."
Lalitha JaganAug 2024
Bamboo Wick Holder
Reviews collected and published through Judge.me on candlemakingsuppliesindia.store. They are general reviews of the wicks and wick tools named on each card, not assessments of the reorder-point method set out below. Wording is unedited.
✓ CSI 464 listed in 500 g, 1 kg, 5 kg and 10 kg ✓ GST invoicing on every order ✓ Larger quantities quoted on WhatsApp
Scaling, Cash Flow & Procurement · Reorder point
Reorder point = daily usage × lead time + safety stock. The formula is easy. The trap for a growing business is feeding it last month's usage. This page builds the reorder point on the month you are about to live through, and shows what happens when you do not.
8.28 kg
reorder point for month 2 of the example (20.70 kg of CSI 464 a month, 7-day lead time, 5 days of safety stock) · wax priced at CSI live pricing, September 2026
Quick answers — read this first
How do I set a reorder point for wax? Reorder point = daily usage × lead time + safety stock. Daily usage is monthly kilos ÷ 30. At 20.70 kg a month, a 7-day lead time and 5 safety days, it is 0.690 × 12 = 8.28 kg. When the shelf drops to that, order.

What changes when I am growing quickly? Use this month's forecast, not last month's actual. A reorder point set on month 1 usage is 7.20 kg. At 15% growth, month 2 needs 8.28 kg. The gap is safety stock that growth spends before a delivery is even late.

What lead time should I use? Your own, measured: from the day you should have ordered to the day the wax is usable. Take the longest of your last three orders. The 7 days on this page is an example, not a CSI delivery promise.

How much should I order at the reorder point? One cycle of forward usage, rounded up to whole packs. CSI 464 costs ₹507.40 a kilo at 1, 5 and 10 kg, so rounding costs nothing extra per kilo. Month 2 of the example is 2 × 10 kg + 1 × 1 kg.
The short answer
Formula: Reorder point = daily usage × lead time + safety stock. With weekly stock checks: order-up-to level = daily usage × (review gap + lead time) + safety stock.
Growth rule: Feed the formula next month's usage. At 15% monthly growth the month 2 reorder point rises from 7.20 kg to 8.28 kg; by month 6 it is 14.48 kg.
Failure case: Stale reorder point (7.20 kg) plus a 12-day delivery in a growing month needs 8.28 kg: short by 1.08 kg, about 6 candles.
A growing business needs a reorder point that grows with it 7.2 kgMonth 118.0 kg used8.3 kgMonth 220.7 kg used9.5 kgMonth 323.8 kg used11.0 kgMonth 427.4 kg used12.6 kgMonth 531.5 kg used14.5 kgMonth 636.2 kg used set on last month's usage set on this month's forecast (labelled) Example: 18 kg in month 1, +15% a month, 7-day lead time, 5 days of safety stock. The gap between each pair is safety stock quietly used up.
Each pair of bars is one month of the worked example. The pale bar is the reorder point you get if you keep using the previous month's usage. The dark bar is the one built on the month you are in. The gap between them is small in any single month, but it comes straight out of your safety stock, and it widens every month you grow.
Straight answer
I'm growing quickly but don't want to run out of wax. How do I set a reorder point based on monthly consumption and supplier lead time?
Use reorder point = daily usage × lead time + safety stock, and feed it the usage of the month you are about to live through, not the month you just finished. Daily usage is monthly kilos ÷ 30. Lead time is your own measured time from ordering to usable wax, taken from your slowest recent order. Safety stock is a buffer in days, often somewhere between half and all of the lead time to start with. In the worked example, a maker uses 18 kg of CSI 464 in month 1 and grows 15% a month. With a 7-day example lead time and 5 safety days, a reorder point built on month 1 usage is 7.20 kg. In month 2 the business actually needs 8.28 kg. If that month's delivery also takes 12 days, the stale reorder point runs dry 1.08 kg short, about 6 candles. Recalculate every month, round the order up to whole packs (CSI 464 is ₹507.40 a kilo at every listed size, so rounding costs nothing extra per kilo), and keep the reorder quantity physically separate so you cannot miss it. I Use 50 Kg of Soy Wax Every Month and My Supplier Takes 10 Days to Deliver — At What Inventory Level Should I Reorder? works the 50 kg a month, 10-day case in full.
One line: a reorder point is only as good as the usage figure you feed it — in a growing business, feed it next month.
The worked example uses Luxury Soy Wax CSI 464, rated up to 10% fragrance load by the wax maker. It costs ₹260.00 for 500 g, ₹507.40 for 1 kg, ₹2,537.00 for 5 kg and ₹5,074.00 for 10 kg: ₹507.40 a kilo at every size above 500 g. That flat price means your reorder quantity can be whatever the arithmetic says, not whatever unlocks a discount.
Shop Luxury Soy Wax CSI 464

The formula, one input at a time

Running out of wax is almost never bad luck. It is a reorder point set on a number that stopped being true.

A reorder point answers one question: how much wax must be on the shelf at the moment you order, so that you do not run out before the delivery is usable? The answer is the wax you will melt while you wait, plus a buffer for things going wrong. That is all the formula says. Each of its three inputs has a trap, and a growing business falls into all three.

Standard reorder-point arithmetic · every input is yours
The three inputs and where each goes wrong
Input How to get it The trap The fix
Daily usage Monthly kilos ÷ 30 Using last month's kilos while sales grow Use this month's forecast; recalculate monthly
Lead time (days) Your order-to-usable time, measured Using the courier's transit days only Include ordering delay, dispatch, transit and unpacking
Safety stock A buffer in days or kilos Setting it once and never revisiting Size it in days so it grows with usage; refine with 3086

Daily usage. Take the kilos of wax you melted last month from your production log, not the kilos you bought. Buying and melting differ whenever stock levels change, and it is melting that empties the shelf. Divide by 30 to get kilos per calendar day. If your records are in candles, multiply by the wax per candle: a 200 g candle at an 8% load holds 184 g of wax, so 100 candles use 18.4 kg.

Lead time. This is the one makers underestimate. It starts the moment stock touches the reorder point, not the moment you get round to ordering. It includes payment, dispatch, transit and the time it takes you to unpack, weigh and shelve the wax. It is your number, measured on your address and your ordering habits. We do not publish delivery times here, and the 7 days in this example is purely illustrative. Take the longest of your last three orders until you have enough history to do better.

Safety stock. The buffer covers two things: deliveries that take longer than usual, and weeks that sell more than usual. For a growing business there is a third: the month is bigger than the one you based the numbers on. Setting safety stock in days of usage rather than fixed kilos is the simplest protection, because days scale automatically when daily usage rises. This page uses 5 days as an example. I Have Enough Raw Materials for 500 Candles but Sales Are Growing Unpredictably — How Much Safety Stock Should I Maintain? compares four ways to size it from your own data.

Measure lead time from the reorder point, not from checkout
Write the date on the reorder card when stock first touches the line, and the date the wax is on your bench. The gap is your real lead time. Makers who do this for three orders usually find it is two or three days longer than they assumed, and that difference alone explains most stock-outs.

Why last month's usage fails a growing business

Here is the example. A maker pours 200 g soy candles at 8% in CSI 464. Month 1 uses 18 kg of wax, about 98 candles. Sales are growing 15% a month, which is the reader's own example rate, not a forecast for your business. Lead time is 7 days and safety stock 5 days, so the reorder point is always 12 days of usage. The question is simply: 12 days of which month?

Example: 18 kg in month 1, +15% a month · 7-day lead time · 5 safety days
Reorder point on last month's usage vs this month's
Month Wax used Daily usage Reorder point on last month Reorder point on this month Safety stock lost to growth
Month 1 18.00 kg 0.600 kg 7.20 kg 7.20 kg 0.00 kg
Month 2 20.70 kg 0.690 kg 7.20 kg 8.28 kg 1.08 kg
Month 3 23.80 kg 0.793 kg 8.28 kg 9.52 kg 1.24 kg
Month 4 27.38 kg 0.913 kg 9.52 kg 10.95 kg 1.43 kg
Month 5 31.48 kg 1.049 kg 10.95 kg 12.59 kg 1.64 kg
Month 6 36.20 kg 1.207 kg 12.59 kg 14.48 kg 1.89 kg

In month 2 the gap is only 1.08 kg. That looks harmless, and in a month where everything else goes to plan, it is. Growth alone eats 0.63 kg of the 3.45 kg safety stock during a 7-day lead time: about 18% of the buffer, gone before anything has gone wrong. The problem is that the buffer exists for the month when something does go wrong.

How a growing business runs dry. Month 2, stale reorder point of 7.20 kg. The order is placed on time, but this delivery takes 12 days instead of 7. Over 12 days at month 2's usage the business melts 8.28 kg. The shelf held 7.20 kg. It runs out 1.08 kg short, roughly 6 candles, or 1.6 days of production with no wax. With the forward-looking reorder point of 8.28 kg, the same late delivery arrives with 0.00 kg still on the shelf. Neither the growth nor the late delivery caused the stock-out on its own. The combination did.

There are two ways to build growth in. The first, used in the table, is to forecast this month's usage from your order book and last month's trend, and set the reorder point on it. The second, for makers who prefer not to forecast, is to size safety stock in days of the current month and recalculate on the first of every month. Both work. What does not work is setting the reorder point once, in a slow month, and leaving it on a sticky note for half a year.

The CSI principle
Set the reorder point on the month the delivery lands in.
Your wax runs out in the future, so the usage that matters is future usage. In a flat business last month and next month are the same number. In a growing one they are not, and the difference is taken straight out of the buffer you thought was protecting you.

Continuous or weekly checks

The reorder point assumes you notice the moment stock touches the line. That is true if you update stock after every pour day. Many small businesses check stock once a week instead. If you do, the formula needs one more term, because stock can fall past the reorder point on Tuesday and nobody notices until the following Monday.

For a weekly check, use an order-up-to level: daily usage × (review gap + lead time) + safety stock. Every Monday, order whatever brings your stock (on hand plus anything already ordered) up to that level. In month 2 of the example, with a 7-day review gap, the level is 0.690 × (7 + 7 + 5) = 13.11 kg. The weekly order is then that level minus what you have. It is a little more wax on the shelf than continuous review, in exchange for only looking once a week.

Same example · weekly stock check · 7-day lead time · 5 safety days
Order-up-to level by month
Month Daily usage Continuous reorder point Weekly order-up-to level Extra wax for weekly checking
Month 1 0.600 kg 7.20 kg 11.40 kg 4.20 kg (₹2,131.08)
Month 2 0.690 kg 8.28 kg 13.11 kg 4.83 kg (₹2,450.74)
Month 3 0.793 kg 9.52 kg 15.08 kg 5.55 kg (₹2,818.35)
Month 4 0.913 kg 10.95 kg 17.34 kg 6.39 kg (₹3,241.11)
Month 5 1.049 kg 12.59 kg 19.94 kg 7.35 kg (₹3,727.27)
Month 6 1.207 kg 14.48 kg 22.93 kg 8.45 kg (₹4,286.36)

The last column puts a price on convenience. In month 6 of the example, weekly checking holds about ₹4,286.36 more CSI 464 than checking after every pour day. Some makers will happily pay that for an hour saved each week. Others will not. Either choice is fine, as long as the formula matches the habit. A continuous reorder point with a weekly habit is the most common hidden cause of emergency orders, which I'm Constantly Placing Emergency Raw-Material Orders — How Do I Calculate Minimum Stock Levels for Wax, Fragrance, Wicks and Jars? deals with directly.

There is a physical version of continuous review that needs no stock counting at all: the two-bin method. Keep the reorder quantity sealed and separate, labelled "reorder when opened". In month 3 of the example that is 9.52 kg, which rounds up to 1 × 10 kg of CSI 464. Pour from the open stock. The day you break the seal on the reserve, you order. It works because the trigger is an action you cannot skip, not a number you must remember to check. Update the size of the sealed reserve when you recalculate each month.

Turning the reorder point into packs

A reorder point in kilos is only useful if you can see it on the shelf in packs.

Round the reorder point up to something you can count at a glance, never down. Then decide how much to order each time. For wax, a common starting point is one month of forward usage, rounded up to whole packs. The table below does that for each month of the example, using the largest CSI 464 packs first. Because CSI 464 is ₹507.40 a kilo at 1, 5 and 10 kg, the mix of packs does not change the price, only the handling.

CSI 464 at ₹5,074.00 / 10 kg · ₹2,537.00 / 5 kg · ₹507.40 / 1 kg · CSI live pricing, 24 September 2026
One month of forward usage, rounded up to packs
Month Forecast usage Packs Kilos bought Order cost
Month 1 18.00 kg 1 × 10 kg + 1 × 5 kg + 3 × 1 kg 18 kg ₹9,133.20
Month 2 20.70 kg 2 × 10 kg + 1 × 1 kg 21 kg ₹10,655.40
Month 3 23.80 kg 2 × 10 kg + 4 × 1 kg 24 kg ₹12,177.60
Month 4 27.38 kg 2 × 10 kg + 1 × 5 kg + 3 × 1 kg 28 kg ₹14,207.20
Month 5 31.48 kg 3 × 10 kg + 2 × 1 kg 32 kg ₹16,236.80
Month 6 36.20 kg 3 × 10 kg + 1 × 5 kg + 2 × 1 kg 37 kg ₹18,773.80

Six months of this pattern buys 160 kg for ₹81,184.00. Rounding up to whole kilos adds less than a kilo a month. On a wax with flat per-kilo pricing, there is no reason to round further than that, and no financial reason to buy several months ahead. Should I Keep More Money in Cash or Use It to Buy Larger Quantities of Candle Raw Materials at Better Prices? compares holding cash against buying larger quantities, and My Candle Business Is Growing but All My Cash Keeps Going Back into Wax, Fragrance Oils and Jars — How Much Raw-Material Inventory Should I Actually Hold? shows what the extra cover costs across all four materials.

The waxes in CSI's listed range price differently, and that changes the pack decision:

Wax needed for month 1 of the example (18 kg) · CSI live pricing, 24 September 2026
Same 18 kg, three soy waxes
Wax Per-kg price by pack Cheapest listed pack mix for 18 kg Fragrance ceiling (wax maker's stated maximum)
Luxury Soy Wax CSI 464 ₹507.40 at 1, 5 and 10 kg ₹9,133.20 up to 10%
Luxury Soy Wax Chunks ₹599.00 at 1 and 5 kg · ₹599.90 at 10 kg ₹10,782.00 up to 13%
Natural Soy Pearl Wax ₹450.00 at 1 kg · ₹424.80 from 5 kg ₹7,722.00 not quoted here — check the product page

Only Natural Soy Pearl Wax has a real pack break: ₹450.00 a kilo at 1 kg, ₹424.80 from 5 kg, a 5.6% saving that stays the same at 10 kg and 50 kg. For that wax, set your reorder quantity in 5 kg multiples and you capture the whole saving without buying further ahead. Switching wax is a formulation decision, not a stock decision, so test any change in your own jars before it reaches a customer.

1
Container soy wax · flat per kilo
Luxury Soy Wax CSI 464
The wax in the worked example. Rated up to 10% fragrance load by the wax maker, and priced at ₹507.40 a kilo from 1 kg to 10 kg. That makes it an easy wax to run on a reorder point: order exactly what the forecast says, in whichever packs are convenient.
Pack Price Per kg Candles at 184 g
500 g ₹260.00 ₹520.00 2.7
1 kg ₹507.40 ₹507.40 5.4
5 kg ₹2,537.00 ₹507.40 27.2
10 kg ₹5,074.00 ₹507.40 54.3
₹93.36 of wax in each 200 g candle at 8% Buy CSI 464
2
Container soy wax · higher stated ceiling
Luxury Soy Wax Chunks
Rated up to 13% fragrance load, the higher of the two stated ceilings in this series. ₹599.00 a kilo at 1 kg and 5 kg. The 10 kg pack is ₹599.90 a kilo, so for this wax the 5 kg is the sensible largest pack for a reorder quantity.
Pack Price Per kg Candles at 184 g
500 g ₹299.00 ₹598.00 2.7
1 kg ₹599.00 ₹599.00 5.4
5 kg ₹2,995.00 ₹599.00 27.2
10 kg ₹5,999.00 ₹599.90 54.3
₹110.22 of wax in each 200 g candle at 8% Buy Luxury Soy Wax Chunks
3
Soy wax · real 5 kg break
Natural Soy Pearl Wax
The one soy wax in the listed range where a bigger pack costs less per kilo: 5.6% less from 5 kg, and no further break at 10 kg or 50 kg. No fragrance ceiling is quoted in this series, so check the product page or ask us on WhatsApp for the wax maker's stated maximum before you formulate.
Pack Price Per kg Candles at 184 g
1 kg ₹450.00 ₹450.00 5.4
5 kg ₹2,124.00 ₹424.80 27.2
10 kg ₹4,248.00 ₹424.80 54.3
50 kg ₹21,240.00 ₹424.80 271.7
₹78.16 of wax in each 200 g candle at 8% at the 5 kg rate Buy Natural Soy Pearl Wax
Argued against our own interest, plainly. A supplier would rather you set a big reorder quantity. For CSI 464 and Luxury Soy Wax Chunks, a bigger order buys no lower rate on our listed prices, and for Chunks the 10 kg is ₹0.90 a kilo dearer than the 5 kg. Order one cycle at a time, recalculate monthly, and keep the cash. The exception is Natural Soy Pearl, where buying in 5 kg multiples saves 5.6%, and that saving is already fully captured at 5 kg.
Growing past 10 kg packs? CSI's listed wax packs stop at 10 kg, with Natural Soy Pearl going to 50 kg. For larger quantities, or to set up a regular order that matches your reorder point, message us on WhatsApp with your monthly usage. No volume discount figure is published, so we quote on the actual order. Diwali is 8 November 2026, so festive wax is worth quoting now.
Ask for a wax quote on WhatsApp

A monthly routine that keeps up

The reorder point is not a one-off calculation. For a growing business it is a monthly habit that takes ten minutes, and the ten minutes are what stop the emergency orders.

1
On the first of the month, write down last month's wax meltedKilos from your production log. If you track candles, multiply by wax per candle (184 g for a 200 g candle at 8%).
2
Forecast this monthLast month × your growth, adjusted for any order you already know about. If you do not want to forecast, use last month and increase safety days instead.
3
Update lead timeCheck the dates on last month's reorder cards. If any delivery took longer than your figure, use the longer one.
4
Recalculate the reorder pointForecast ÷ 30 × (lead time + safety days). For month 2 of the example: 0.690 × 12 = 8.28 kg.
5
Resize the sealed reserveIf you use two bins, top up or split the reserve to match the new reorder point, rounded up to packs.
6
Set the order quantityOne month of forecast usage, rounded up to whole packs, unless a real pack break or a known event changes the case. Write it on the reorder card so ordering takes one minute.

Do the same for wicks and jars, which also stop production when they run out. They follow the same formula in units instead of kilos. Fragrance oils are different, because each scent runs at its own speed; My Candle Business Uses 20 Different Fragrance Oils — How Do I Set Separate Reorder Levels for Fast-Selling and Slow-Selling Scents? sets reorder levels scent by scent. If two or more materials keep running out at different times, I'm Running Out of One Raw Material While Having Months of Another — How Do I Synchronise Wax, Fragrance, Wick and Jar Purchasing with Actual Production? shows how to line their reorder cycles up.

Seasonal peaks sit outside this routine. A reorder point handles steady growth. It does not handle a month that is three times the size of the last one, because the buffer is sized for normal variation, not for a festival. Plan Diwali and the November–February wedding season as a separate build-up. My Candle Sales Double During Diwali — How Early Should I Start Increasing Wax, Fragrance Oil, Wick and Jar Inventory Before the Season? covers how early to start.

Twelve days of last month's wax is not twelve days of this month's. Growth spends your safety stock before anything has gone wrong.
— CandleMakingSuppliesIndia

If you would like help checking the arithmetic, send us your monthly usage for the last three months and your usual order dates on WhatsApp. We can suggest pack combinations on our listed prices and quote anything beyond them.

Why trust this guide

CANDLEMAKINGSUPPLIESINDIA supplies raw materials, not finished candles. The easy advice for a wax supplier is to hold more wax. This page instead sets the smallest reorder point that keeps you safe, and says plainly that on our listed prices a larger wax order buys no lower rate for CSI 464 or Luxury Soy Wax Chunks.

Wax prices are CSI live pricing, pulled on 24 September 2026. Reorder points, order-up-to levels, pack rounding and order costs are standard inventory arithmetic on those prices and the stated example, shown to two decimals so you can check them.

The 18 kg starting month, 15% growth, 7-day lead time, 12-day late delivery and 5 safety days are illustrations, not CSI delivery times or forecasts. Replace them with your own. For quantities beyond the listed packs, GST invoicing or product documentation, message us on WhatsApp at +91 7397976926.

Frequently asked questions

What is the reorder point formula for candle wax?
Reorder point = daily usage × lead time + safety stock. Daily usage is monthly kilos ÷ 30, lead time is your measured order-to-usable time in days, and safety stock is a buffer, easiest to set in days of usage.
How do I calculate reorder point when sales are growing?
Use this month's forecast usage rather than last month's actual, and recalculate monthly. In the example, 15% growth lifts the month 2 reorder point from 7.20 kg to 8.28 kg. Sizing safety stock in days also scales it automatically.
How much safety stock of wax should I keep?
Start with a number of days between half and all of your lead time, then refine with real data. I Have Enough Raw Materials for 500 Candles but Sales Are Growing Unpredictably — How Much Safety Stock Should I Maintain? compares fixed days, percentage, max–min and statistical methods.
What if I only check my stock once a week?
Use an order-up-to level instead: daily usage × (7 + lead time) + safety stock. Every week, order enough to bring stock on hand plus stock on order up to that level.
What is the lead time for CSI wax orders?
We do not publish delivery times on this page. Measure your own from your last few orders, from the day stock hit the reorder point to the day the wax was usable, and use the longest.
Is 10 kg of soy wax cheaper than 5 kg?
Not on CSI's listed prices for CSI 464 (₹507.40 a kilo at both) or Luxury Soy Wax Chunks (₹599.00 a kilo at 5 kg, ₹599.90 at 10 kg). Natural Soy Pearl Wax is ₹424.80 a kilo at 5, 10 and 50 kg, 5.6% below its 1 kg price.
Order on the month ahead
Daily usage × lead time + safety stock. Feed it next month, recalculate monthly, and round up to whole packs.
Luxury Soy Wax CSI 464 at ₹507.40 a kilo, Luxury Soy Wax Chunks at ₹599.00 and Natural Soy Pearl Wax from ₹424.80 a kilo in 5 kg packs. Send us your usage and we will help size your regular order.
Shop candle wax Ask about wax quantities on WhatsApp
Editorial standards & sources
About this guide: Written by the CANDLEMAKINGSUPPLIESINDIA team. Product recommendations reflect the CSI range. The reorder-point and order-up-to method is standard inventory practice and applies to any supplier's wax.

Customer reviews: The six reviews at the top of this page are genuine, published Judge.me reviews left by CSI customers on the product pages named on each card — Eco Candle Wicks, Premium Candle Wicking Needle and Bamboo Wick Holder. They are general product reviews, not assessments of the reorder-point method set out here. Names, star ratings, dates and products are as recorded by Judge.me and wording is unedited. "Verified buyer" appears only on the three reviews Judge.me recorded as verified — Monika Deep, Subhankar Roy and Sneha Tamang; the reviews from Ashwini, LJ and Lalitha Jagan are published but not recorded as verified, and carry no badge.

Figures pulled 24 September 2026, CSI live pricing: Luxury Soy Wax CSI 464 ₹260.00 / 500 g, ₹507.40 / 1 kg, ₹2,537.00 / 5 kg, ₹5,074.00 / 10 kg. Luxury Soy Wax Chunks ₹299.00 / 500 g, ₹599.00 / 1 kg, ₹2,995.00 / 5 kg, ₹5,999.00 / 10 kg. Natural Soy Pearl Wax ₹450.00 / 1 kg, ₹2,124.00 / 5 kg, ₹4,248.00 / 10 kg, ₹21,240.00 / 50 kg.

Non-price figures and assumptions: Example: 18 kg of wax in month 1, growing 15% a month; lead time 7 days; a late delivery of 12 days; safety stock 5 days; weekly review gap 7 days. Daily usage = monthly kilos ÷ 30. Wax per candle is 184 g (200 g candle at an 8% load). Pack rounding rounds each month up to whole kilos, then splits into 10 kg, 5 kg and 1 kg packs. Fragrance ceilings of up to 10% (CSI 464) and 13% (Luxury Soy Wax Chunks) are the wax makers' stated formulation maximums, not regulatory limits; no ceiling is quoted here for Natural Soy Pearl. None of these figures is a CSI delivery time or forecast. Prices and availability change — the linked product pages are always authoritative.